Friday, October 19, 2007
Inspection
Oh, there's that lynch pin we've been looking for. The electrical inspection was completed and approved today, so the guys can now close up the walls and prep for paint. The base cabinets should be in in a week and we are about two weeks from doing the floor. So appliances should be installed in about two and a half weeks (Eirik is very excited about this bit). After the appliances is the counter top install, sink and faucet and then it's just finishing touches.
Saturday, October 13, 2007
Upper Cabinets
No More Holes
Here and There
This past week has been filled with some of those small jobs that weren't especially visible but necessary just the same. One of those jobs was removing the header from the old pantry.

Cabinets will go here. Level is good. And yes, if you zoom in super-close, it is actually very level.

This is the vent pipe from the old stove. The new stove will be in a different location and has different venting requirements, so we can't re-use this one.

Cabinets will go here. Level is good. And yes, if you zoom in super-close, it is actually very level.

This is the vent pipe from the old stove. The new stove will be in a different location and has different venting requirements, so we can't re-use this one.
Tuesday, October 9, 2007
Mystery Circle Thingies
Little Bits
The guys were only here for a few hours this afternoon and got a couple of little things done.
Several of the outlets and switches will be mounted under the cabinets, so they got started running the wires for that on a couple of the upper cabinets in the kitchen.


They also punched a wire through into the living room for the thermostat since the wall where it used to live is gone. I think we're going to ask them to move this a little.
Several of the outlets and switches will be mounted under the cabinets, so they got started running the wires for that on a couple of the upper cabinets in the kitchen.


They also punched a wire through into the living room for the thermostat since the wall where it used to live is gone. I think we're going to ask them to move this a little.
New Design Feature?
No, not a new modern art design feature - just wire fish holes so that Raul could get wire from the switches to the fixtures.

This is the dining room wall. The blue circles are where the new sconces will go.

Dining room recessed lights.

Kitchen recessed lights. The blue guy is where one of the pendant lights will go.

This is the dining room wall. The blue circles are where the new sconces will go.

Dining room recessed lights.

Kitchen recessed lights. The blue guy is where one of the pendant lights will go.
Monday, October 8, 2007
Outlets
The microwave will be located along this wall. The fridge used to be here, so we're going to re-use that outlet.

The guys also relocated the wiring Eirik did for internet, etc. to this wall because the wall it used to be on no longer exists.

They also moved the other wiring box that used to be in the cabinet on kitchen side. You can see it now down there under the window. There's also going to be a scone on the wall to the right of the window. The blue box down there is where we can plug in all our gadgets =)

It's handy to be able to plug things like mixers in when you're working at an island - that's what these yellow wires are for.


The guys also relocated the wiring Eirik did for internet, etc. to this wall because the wall it used to be on no longer exists.

They also moved the other wiring box that used to be in the cabinet on kitchen side. You can see it now down there under the window. There's also going to be a scone on the wall to the right of the window. The blue box down there is where we can plug in all our gadgets =)

It's handy to be able to plug things like mixers in when you're working at an island - that's what these yellow wires are for.